The site
A large hillside home in Los Gatos was up on cribbing while the new basement was dug out underneath. The basement needed drainage lines out to the hillside, and the only way out was under the house and down a landscaped slope.
Our approach
We brought the drill rig down into the basement and dug two entry pits in the corner. From there we drilled two shots on about a 4% downhill grade, out to two exit pits on the hillside. Each bore was pre-reamed and then reamed to 12 inches. The hydrovac pulled drill mud from the pits the whole time, so the basement stayed workable.
The result
Two bore runs, each with two 4-inch conduits, now carry the basement drainage out to daylight. Nothing was trenched through the foundation area or the hillside landscaping, and the general contractor kept working on the basement around us.